Critiques/2010-08-24/Sug/0021
From PCSAR
(Difference between revisions)
Line 18: | Line 18: | ||
Action: | Action: | ||
- | * Train senior PCES | + | * Train senior PCES in SAR approach. |
* General training - every team needs a leader. | * General training - every team needs a leader. | ||
** Renew training for all members, including senior members, that whenever together must identify a team leader. | ** Renew training for all members, including senior members, that whenever together must identify a team leader. | ||
Reviewed at [[Members:Preplan/2010-11-16|2010-11-16 Preplan meeting]]. | Reviewed at [[Members:Preplan/2010-11-16|2010-11-16 Preplan meeting]]. | ||
+ | |||
+ | Preplan 2012-09-18 | ||
+ | * refer to train committee |
Revision as of 02:55, 20 September 2012
Suggestion #21: No PCSAR team leader in the field.
- Committee handling: training
- Value to PCSAR mandate: high
- Difficulty to implement: easy
Original issue was "A bear had been seen before, but not all knew that a bear was in area." but the root cause was that a safety briefing was missed, in fact there was no briefing, because there was no team leader in the field.
Happens a lot when we are working with other agencies. Lack of our leadership when we work with PCES. We assume they will do it.
First member that arrives should assume leadership for our organization.
How to coordinate between 2 different agencies.
Who know that the bear was there? SRD knew? There's always a bear in that area. Was it a risk?
Action:
- Train senior PCES in SAR approach.
- General training - every team needs a leader.
- Renew training for all members, including senior members, that whenever together must identify a team leader.
Reviewed at 2010-11-16 Preplan meeting.
Preplan 2012-09-18
- refer to train committee
Facts about Critiques/2010-08-24/Sug/0021RDF feed
Committee handling | Suggestion/Committee/List/training + |
Description | No PCSAR team leader in the field. + |
Difficulty to implement | easy + |
Full page name | Critiques/2010-08-24/Sug/0021 + |
Sequence number | 21 + |
Suggestion list | Critiques/2010-08-24 + |
Value to PCSAR mandate | high + |